Texas pauses new data center grid connections
August 07, 2026
Texas pauses new data center grid connectionsAugust 07, 2026 On June 10, 2026, Governor Greg Abbott of Texas issued a directive to the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) to take steps to protect residential ratepayers in Texas from the costs of data center expansion. That directive required the PUCT to take action to ensure that data center interconnections will result in reduced residential electrical bills and that data centers pay for all their required infrastructure costs. The Governor’s June 10th Directive additionally required both the PUCT and ERCOT to review their existing authority to identify necessary actions to safeguard Texans against burdens placed on Texans by data center expansion in the state. On August 3, 2026, Governor Abbott issued an even more consequential directive to the PUCT and ERCOT that may result in a substantial disruption of new data center development within the state. The August 3rd Directive orders the PUCT and ERCOT to “conduct a comprehensive verification and audit of all data centers advancing through ERCOT’s interconnection process before any additional data centers are approved to move forward” and provides that any project that does not comply with applicable requirements and state law will be denied connection to the Texas grid. The directive states that this audit and pause on interconnections is necessary because of “[t]he failure of some data centers to comply with the PUCT’s survey measuring water and power usage . . ., [which] hinders [the PUCT’s] ability to make fully informed decisions.” The audit will require a developer to provide detailed information on:
Any data center project that fails to comply with the verification and audit process will be denied. It would appear that data centers with 100% behind the meter power or that are otherwise not interconnecting through ERCOT, such as interconnections in portions of the state not connected to the ERCOT grid (primarily far east and west Texas) would not be affected by the audit. ERCOT will not share initial determinations of Batch Zero status today, as required in Batch Zero Rules. ERCOT has announced that it will instead apply for a good-cause exception from the PUCT, to be considered at the August 20, 2026 Open Meeting. If a data center is in the queue and has done everything right, it does not appear that anything in the orders would impact its ability to get power; though, there will be a delay, and no one knows how long a delay. It is clear that no new data center interconnections will be approved until the audit is complete. At this point, there is no indication of how strict the audit will be. Whether data centers are forced to reapply for minor errors or if this will be limited to real problems with the content of the application remains to be seen. ___________ If you have any questions about this Legal Briefing, please feel free to contact any of the attorneys listed or the Eversheds Sutherland attorney with whom you regularly work. Latest InsightsLatest News
Latest Events
legal updates August 05, 2026 EU Pay Transparency Directive: Data protection legal updates August 05, 2026 Commercially Connected shorts - 5 August 2026 legal updates August 05, 2026 Continuation Vehicle Finance: Key Issues for Lenders in UK and Europe legal updates August 04, 2026 Germany: Government adopts Grid Package (Netzpaket) client news July 30, 2026 Eversheds Sutherland Advises Johnson Matthey on Acquisition of CORMETECH In... client news July 24, 2026 Advising Johnson Matthey on completion of the sale of its Catalyst Technolo... client news July 10, 2026 Setting sail: Eversheds Sutherland advises senior management of D-Marin on ... firm news July 10, 2026 Eversheds Sutherland advises OCBC on the landmark secondary dual listing of... virtual UAE - Employment law in the Dubai International Financial Centre September 10, 2026 9.30am - 1.30pm (GMT) Virtual in-person Managing AI use in the workplace: what every UK HR team needs to know September 10, 2026 9.30am - 1.00pm (BST) London, United Kingdom in-person Basic foundations of US employment law September 17, 2026 9.30am - 4.30pm (GMT) London, United Kingdom in-person 2026 BDC Roundtable September 23, 2026 Washington DC, United States |